The Illinois Theater Company
An ad hoc citizens committee had been soliciting people to purchase stock to make the new opera house a reality. By early 1907, as reported in the Champaign Daily Gazette on 8 February, subscribers had taken $34,000 worth of stock out of the $40,000 goal. 1
The subscribers had met in the court house on 6 February and formed a temporary organization to take charge until the company was incorporated. C. N. Clark was elected President, Dr. W. F. Burris vice-president, George Busey, treasurer, and Zach G. Oldham secretary. N. W. Busey, T. B. Thomby, and C. N. Clark were appointed a building committee. 2
“Final plans for the proposed Illinois Theatre in Urbana, were presented to the stockholders at a meeting Monday evening. They were approved, and it was decided to submit them to contractors for estimates as to the cost, a report to be made in about two weeks,” reported The Champaign Daily Gazette on 9 April, 1907. 3
The article went on to give some preliminary descriptions of the theatre, and announce that about $4,000.00 worth of tickets for the opening night’s performance had been sold. The promoters had maintained that $10,000.00 had been necessary to authorize beginning construction. Once the bids were received, they would meet to decide whether or not to proceed. 4
A very short article in The Champaign Daily Gazette of 23 April, 1907, reported: “A meeting of the building committee of the new opera house company will be held Thursday evening to open the bids of the contractors. A meeting of the stockholders will be held later. It is said some of the stockholders will withdraw their stock subscriptions if saloons are voted out; but it is thought there will be no difficulty in finding new people to take their holdings.” 5
The Illinois Theatre Company stockholders met in the supervisors’ rooms of the court house Monday evening, 17 June 1907. Stockholders present represented about 80 percent of the stock and all were in favor of starting the building, and therefore authorized the building committee to let the contract for the new playhouse. 6
Contractor William F. Baird had the winning bid of $37,367, for the building alone. With anticipated costs for decorating, interior furnishings, and stage appliances, the completed building was expected to cost in the neighborhood of $50,000. 7
The committee had made some changes from the original plan in order to reduce costs. Few changes were made in the interior, but the exterior design was made plainer than originally planned. Another change was in the location, shifting the building to the extreme western end of the flatiron property, at the head of Birch Street, fronting on Railroad Street, where the street car line ran. A secondary entrance from Main Street was to be included, but an originally planned corridor connecting the south and north entrances was eliminated mainly due to the size of the lot. The new location had been donated by the stockholders of the Elk Building Association. 8
The committee still hoped to raise $10,000 by the sale of first night tickets, with $4,000 already subscribed. These funds were to be earmarked to the finishing of the theatre. 9
The contract stipulated, what turned out to be overly optimistic, that the building was to be completed by 15 November. 10